Project Name | Client / Owner | Project Output | Period |
Piping Process Area for Batik Sugar Mill & Power Plant Project | PT Muria Sumba Manis | Piping Work | 2020 - 2021 |
General Mechanical Work Package 2 (Process Area 2 and Offsite Area) JTB Project | PT Rekayasa Industri | Mechanical Work | 2020 - 2021 |
MEP Work Build C/D/G Warehouse Buildings Refurbishment in Mechanical Electrical Plumbing Construction | PT Karyadibya Mahardhika | Electrical Work | 2020 |
ME Building (Lighting Facilities, Fire Alarm System, Telecommunication & LAN System, Fire Fighting Facilities) Mechanical Installation and Electrical Work | PT JGC Indonesia | Electrical Work | 2019 - 2020 |
Electrical & Instrumentation Work Plant Industrial Complex PT MNA Serang | PT Multinas Nabati Asahan | Electrical Work | 2019 |
Pekerjaan Piping di PP Debottlenecking - Candra Asri Project | PT JGC Indonesia | Piping Work | 2019 |
Steel Structure Erection PLTU Sulsel Barru-2 CFSPP 1X100MW | PT Wijaya Karya | Steel Structure Erection | 2019 |
Installation Steel Steel Structure Halmahera Project | PT Wijaya Karya | Installation Steel Structure | 2018-2019 |
Installation Electrical & Instrument Work East Halmahera Ferronickel Plant Project | PT Wijaya Karya | Electrical Wokr | 2018 |
Pekerjaan Tambah Daya Tahap 2 Electrical Work | PT Indofood Sukses Makmur | Electrical Work | 2018 |
01 Jul 2020
Piping Process Area for Batik Sugar Mill & Power Plant ProjectPT Muria Sumba Manis